New England House – ‘High level’ timetable
|
Task |
Timetable |
|
Develop Design/Planning application |
Jan – Jul 2021 |
|
Submit Planning Application |
Jul - Dec 2021 |
|
Planning Determination Period |
Dec 2021 – Mar 2022 |
|
Planning Conditions |
Jul 2021 – Mar 2022 |
|
Technical Design Period (RIBA Stage 4) |
Jul 2021 – Mar 2022 |
|
Measurement and Pricing |
Apr 2022 – Jul 2022 |
|
Mobilisation and Tender Evaluation |
Aug 2022 – Dec 2022 |
|
Start on site |
Jan 2023 |
|
Build Period (18 months) |
Feb 2023 to Jul 2024 |